SARS - Integration

80%

Status

In Process [In Process]

80% complete, updated on Thu 4/16/26 2:41 PM by Jeannette Jasmin Ramos

Changed Percent Complete from 60% to 80%.
SARS has been deployed into SaaS PROD by ABCloudz and the test plan has been developed by the information analysts. 

Testing is scheduled for Sprint 3 (April 20-24). 

Details

Dates
Tue 9/2/25 - Fri 2/27/26
Acct/Dept
Technology Services & Support
Type
Information Technology Projects / Information Technology Projects
Health
Green - On track
Program(s)
Created
Tue 9/2/25 12:15 PM
Modified
Thu 4/16/26 2:41 PM
Benefit/Purpose
Briefly describe what you hope to achieve by executing the project, including anticipated benefits.
The purpose of this project is to successfully integrate SARS Track (Student Advising and Reporting System) with the Ellucian SaaS environment ensuring current functionality is maintained.
Deliverables Requested
List or summarize all specific deliverables resulting from this project. What will the project produce or deliver? These should include items that are specific, measurable, achievable, realistic, and time bound.
(1) Ensure consistent data flow and synchronization from SARS to Banner

Program Review & Participatory Governance

Budget Health
Green
Resource Health
Green
Schedule Health
Green

Alternate Manager(s)

Sponsor